We’re here to help answer your questions. Browse the frequently asked questions below, and if you don’t see what you’re looking for, contact us online or call 1-800-632-6605.
General Questions
On-site generation is a service offering available to Idaho Power customers who install electricity-generating equipment at their home or business to meet some of their energy needs while remaining connected to Idaho Power’s grid. This offering is available to Idaho residential customers (Schedule 6), Idaho small general service customers (Schedule 8), and Idaho and Oregon large general, large power and irrigation service as well as Oregon residential and small general service customers (Schedule 84).
Idaho Power customers can install solar or other renewable energy systems to offset some or all of their energy use. Systems that are connected to the grid are called “interconnected.” With an interconnected system, energy flows two ways between the electrical grid and your home. At times, the solar or renewable system will produce more energy than the home/business needs. At other times the home/business will need to draw electricity from Idaho Power. Alternatively, a system can be designed as “non-export” to prevent excess energy from flowing to the grid.
Idaho large general service (Schedule 09), large power (Schedule 19) and irrigation (Schedule 24) customers may connect an exporting system with a total nameplate capacity equal to or less than the greater of: (a) the greatest monthly Billing Demand established during the most recent 12- month period which includes and ends with the current Billing Period, or (b) 100 kW.
Oregon large general service (Schedule 09), large power (Schedule 19) and irrigation (Schedule 24) customers may connect an exporting system with a total nameplate capacity of up to 100 kW. There is no size limit for non-exporting systems for these customer groups.
For exporting systems over these limits, refer to Generator Interconnection.
- Idaho residential customers – Schedule 06, Residential Service On-Site Generation
- Idaho small general service customers – Schedule 08, Small General Service On-Site Generation
- All Oregon customers*, and Idaho large general, irrigation and large power customers – Schedule 84, Large General, Large Power, and Irrigation On-Site Generation Service, and their standard retail service schedule (i.e. Schedule 9: Large General Service).
For Idaho residential (Schedule 06) and large general service (Schedule 09) customers, upon completion of the interconnection process, customers will take service under the Standard Rate option. Customers may request to transition to the Time of Use option if applicable after receiving final permission to operate by contacting the customer service center.
*Oregon customers will take service under the December 2023 version of Schedule 84.
In the meantime, Oregon customers will continue to take service under the version of Schedule 84 that was in effect on December 18, 2023. As a result, some eligibility and system criteria will be different for Oregon customers until approved by the OPUC. These include:
- Oregon Large General Service (Schedule 09), Irrigation (Schedule 24), and Industrial (Schedule 19) customers will be limited to systems with a total nameplate capacity of 100 kW or less.
- AC-coupled batteries will count towards the total nameplate capacity used to evaluate maximum allowable systems sizes: 25 kW for Oregon Residential (Schedule 01) and Small General Service (Schedule 07) customers; 100 kW for Oregon Large General, Irrigation, and Industrial service customers.
- The Idaho general rate case changes do not affect Oregon customers. Idaho Power has filed a general rate case with the OPUC that is under consideration.
Additionally, Idaho Power’s rules and pricing structures are not contracts and are subject to change at any time with approval from the IPUC. Modifications to the compensation structure could result in changes to how excess energy sent back to the grid by the customer is measured and credited and the value of that credit. Those changes could impact any savings realized from a rooftop solar system and potential payback on the investment.
When an energy storage device is paired with a generating system, the total nameplate capacity depends on whether it is DC-coupled or AC-Coupled. For example, if a battery storage device uses the same inverter as the solar generation system, it is DC-Coupled. If the solar system and battery have separate inverters, the battery is AC-coupled. The total system size for generation systems with energy storage devices will be calculated as follows:
- DC Coupled: For energy storage devices that are DC coupled, the total nameplate capacity of the system is defined by the inverter (kilovoltampere [kVA]).
- AC Coupled: For AC coupled energy storage with an exporting system, the total nameplate capacity is the total nameplate capacity of the generation system plus the energy storage system on the customers’ side of the interconnection point (i.e., the AC capacity of the solar PV system plus the AC capacity of the battery.)
For exporting systems, energy storage capacity shall not be used to calculate the allowable capacity limits set in Schedules 6, 8 and 84 (Idaho customers only). AC coupled storage will count towards the total nameplate capacity values used for Feasibility Reviews for exporting systems as outlined in Schedule 68 and towards capacity limits for Oregon customers.
Energy Storage installed without a generating source must be installed as a non-exporting system under the rules of Schedule 68. (See Non-Export section below for more details).
PVWatts Calculator is an online tool developed by the federal government for estimating solar generation based on geographic location and system design.
To use PVWatts to evaluate different system sizes, input your city, solar size in kilowatts (kW) and the calculator will estimate solar electricity generation by hour for a full year.
Recent Changes to On-site Generation
On December 29, 2023, the Idaho Public Utilities Commission (IPUC) approved changes to Idaho Power’s on-site generation offering. Effective January 1, 2024, Idaho customers with non-legacy on-site generation systems will see changes to billing, compensation structure, and system size limitations.
This ruling by the IPUC concludes a regulatory process that included input and participation from parties including Idaho Power, customer groups, environmental groups, and the public. Idaho Power’s goal in this case was to modernize the 20-year-old compensation structure for on-site generation and ensure prices for excess energy are fair and equitable for all customers.
- Billing changed from net monthly billing to real-time net billing.
- The export credit rate (ECR) changed from a kilowatt-hour (kWh) credit, valued around 10 cents for residential customers, to a financial bill credit ranging from approximately 4.8 to 17 cents per kWh, depending on the time of day the energy is sent to Idaho Power’s electrical grid. The ECR value will be updated annually beginning in spring of 2025.
- KWh credits accrued before the new structure was implemented will carry forward and be applied throughout 2024 as they would have prior to the change. On December 31, 2024, any remaining kWh credits will be converted to a financial credit using a blended average retail energy rate for the customer’s class.
- The annual credit transfer eligibility requirements for non-legacy customers are different, as those customers may transfer excess financial credits to other accounts in their name where the energy is for their own use.
- The system eligibility size cap will be also modified for commercial, industrial, and irrigation customers to the greater of 100 kW or that customer’s demand. The energy storage capacity will be excluded from the determination of a project size cap for all customers.
Idaho Residential and Small General Service (Schedules 6 and 8):
- Customers who interconnected their system by December 20, 2019, or
- Customers who submitted an on-site generation application on or before December 20, 2019, and provided evidence of a binding financial commitment for the on-site generation system by January 19, 2020, and who completed the interconnection process by December 20, 2020.
Idaho Large Commercial, Industrial and Irrigation (Schedule 84):
- Customers who interconnected their system by December 1, 2020, or
- Customers who submitted an on-site generation application on or before December 1, 2020, and interconnected their system as a two-metered system by December 1, 2021.
In addition to the changes associated with on-site generation, on December 28, 2023, the IPUC approved a settlement regarding Idaho Power’s general rate case in Idaho. The settlement calls for an overall rate increase of $54.7 million, or an average of 4.25% for Idaho customers. These new rates went into effect on January 1, 2024 for all customers (including those with on-site generation). For 2024, the new rates include an increase in the fixed monthly service fee from $5 to $10 for residential customers and from $5 to $25 for small general service customers.
In our request to the OPUC, Idaho Power is proposing that customers who have active systems as of February 29, 2024, or who have submitted an application by February 29, 2024, receive legacy status and continue to take service under the Net Energy Metering (1 to 1 kilowatt-hour [kWh] usage offset) until December 1, 2045. After February 29, 2024, new applications received for a new or expanded on-site generation system will be considered “Non-Legacy Systems” and subject to the rules currently in place in our Idaho service area. Idaho Power is requesting these changes become effective June 1, 2024.
Idaho Power’s Idaho Schedule 6 (Residential Service On-Site Generation), Schedule 8 (Small General Service On-Site Generation), Schedule 68 (Interconnections to Customer Distributed Energy Resources), and Schedule 84 (Large General, Large Power, and Irrigation On-Site Generation Service) set forth the provisions which govern its on-site generation service offerings.
If approved as filed, as an Oregon customer your charges from Idaho Power are outlined in your applicable Oregon service schedule, whereas treatment of excess net energy from your on-site generation system will be outlined in the applicable Idaho on-site generation schedule. For customers with Legacy systems, the on-site generation credit structure is “Net Energy Metering” (or the 1-to-1 structure). For customers with Non-Legacy systems, the on-site generation credit structure is “Real-Time Net Billing.” Under real-time net billing, a customer’s grid usage will be measured separately from their excess generation. The grid usage will be billed under the customer’s applicable retail rate, while the customer’s exported energy will receive a value-based credit (the export credit rate).
Idaho tariff schedules are available on our website. The following table shows the Idaho schedules Oregon on-site generation customers can reference for more information.
Current Service Schedule | Applicable Idaho Schedule |
---|---|
Oregon Residential Service (Schedule 1) | Idaho Schedule 6 & Idaho Schedule 68 |
Oregon Small General Service (Schedule 7) | Idaho Schedule 8 & Idaho Schedule 68 |
Oregon Large General, Large Power, and Irrigation Service (Schedule 9, 19 & 24) | Idaho Schedule 84 & Idaho Schedule 68 |
Connecting Your System
Idaho Power also requires an AC disconnect switch on the customer’s side of the meter. Breakers do not meet these requirements. AC disconnects and meters must be readily accessible to Idaho Power 24/7. An overview of the interconnection requirements and a link to the rules as outlined in Schedule 68 Interconnections to Non-Utility Generation are available at liuxuebbs.net/customerGeneration. The specific requirements for the AC disconnect are listed in Schedule 68.
Making changes to an existing service will require the service to comply with the current Customer Requirements for Electric Service, including requirements for service and panel upgrades and meter accessibility.
The first Idaho Power inspection is conducted at no charge. A return trip charge of $52 may be billed to the customer each time Idaho Power personnel are dispatched to the job site but are unable to conduct the on-site inspection due to one or more of the conditions not being met that had been certified as complete by the customer or installer on the System Verification Form. This charge will appear on the customer’s bill the following month.
Making changes to an existing service requires the service to comply with the current Customer Requirements for Electric Service. There may be additional costs, if you upgrade your service or panel or if your meter does not meet the accessibility requirements.
- The system does not generate. This is usually due to a breaker being off or an issue with the inverters (e.g., inverters were not programmed, were not turned on, or have a fault).
- During the grid outage simulation, the inverter reconnects faster than the required 5-minute delay.
- There is no AC disconnect for the generation system or the AC disconnect does not meet the requirements in Schedule 68.
- The AC disconnect and meter are not accessible (behind a locked gate or in a building).
- A battery storage system was installed but not disclosed on the System Verification Form.
- The battery storage system is not working.
- The generation system installation was not finished.
- Smart inverters must conform to the latest Institute of Electrical and Electronics Engineers (IEEE) 1547 standards and be certified by the Underwriters Laboratory (UL) 1741 standard, which complies with the latest IEEE 1547 standards. Idaho Power requires inverters that comply with IEEE 1547-2018 and are UL 1741 SB certified.
- System Modifications that (1) do not replace or add inverters, (2) are like for like as the result of warranty inverter replacements, or (3) rely on an inverter that is required to meet the original inverter specifications for the Customer Generator System to properly function, may be considered exempt from the smart inverter requirement.
There are two configurations for energy storage devices (such as batteries): those that share an inverter with a generation facility (direct current [DC] coupled); and those that have a standalone inverter (alternating current [AC] coupled). For exporting systems, both configurations may export power onto Idaho Power’s system once the customer has completed the interconnection process. Energy storage devices not coupled with a generation facility taking service under Schedule 6, 8, or 84 (exporting system) may not export energy onto Idaho Power’s system and must take service under the non-export provisions of Schedule 68.
Managing Your System
Modifications to customer generation systems that increase the total nameplate capacity of the system or modify the system in any way (including inverter replacements) that may impact the safety or reliability of Idaho Power’s electrical system are considered system modifications. Customers planning modifications must complete the interconnection process including a new application, $100 fee and system verification form. Common modifications requiring an application include:
- Inverter additions or changes (including like for like and warranty replacements or installing a different inverter model)
- Module replacements or additions that increase the total DC capacity for systems originally approved before May 1, 2020.
- Adding energy storage (batteries)
Some scenarios do not require an application and fee, but Idaho Power does require that customers fill out a new system verification form notifying us of the change. Scenarios include:
- Module changes for systems approved after May 1, 2020
- Battery replacements (like for like) or removal
- Removing inverters (and not replacing)
If you aren’t sure, please reach out to cg@liuxuebbs.net to determine if an application is needed.
Note: Systems applying for modifications must meet the requirements in place today. Modifications may also require a state/city electrical inspection. Be sure to check with your authority-having-jurisdiction to ensure the work complies with all electrical codes.
System Modifications that (1) do not replace or add inverters, (2) are like-for-like as the result of warranty inverter replacements, or (3) rely on an inverter that is required to meet the original inverter specifications for the customer generator system to properly function, may be considered exempt from the smart inverter requirement.
Idaho Large General Service, Irrigation, and Large Power Schedules: In order 34854, the IPUC granted Legacy status to on-site generation systems that were installed or purchased by December 1, 2020. Additional eligibility criteria for Legacy status were outlined in the orders. Legacy systems will take service under the Schedule 84 tariff rules in place on December 1, 2020, until December 1, 2045.
Not sure if your system is a Legacy system? Call Idaho Power’s customer solutions advisors at 1-800-632-6605 to confirm your system’s status.
A customer who moves into a property with a legacy net-metering system will inherit the legacy system.
When a customer moves from a property with a legacy system, that customer does not get to take the legacy status of the system with them to their next property.
If a system is offline for more than six months, or is moved to another site, the legacy status of the system is forfeited.
If a customer expands their system, the expansion must be metered separately to retain the legacy status of the original system. If the expansion is not metered separately, the entire system will lose legacy status.
To allow for the replacement of degraded or broken panels, the customer may increase the capacity of their legacy system by no more than 10% of the originally installed nameplate capacity or 1 kilowatt, whichever is greater.
Modifications to Legacy systems are allowed; however, if generating capacity is added, the way in which the new system is connected to the grid could result in forfeiture of the Legacy status of the existing system. The added generation system (i.e. both the new panels and associated inverters) must be metered separately from the Legacy system to retain Legacy status for the existing system. The new portion of the system will not receive Legacy status and will take service under the rules in place at that time and will be subject to future changes in the billing and compensation structure. If the generating capacity increases and the expansion is not separately metered from the Legacy system, Legacy status will be forfeited.
Non-Legacy systems can replace broken panels following the process for modifying systems. For more information, read the FAQ “What if I want to expand or modify my system?”
For Legacy systems, the Idaho Public Utilities Commission allows for replacing degraded or broken solar panels without affecting a system’s Legacy status if specific conditions are met. When replacing panels, customers may increase the Legacy system’s capacity by no more than 10% of the initially installed nameplate capacity or 1 kW, whichever is greater. The total number of panels must remain the same or less than the initially installed system. Customers planning to make system modifications must follow the process for modifying systems. For more information, read the FAQ “What if I want to expand or modify my system?”
Systems that are offline for more than six months will be removed from the on-site generation rate and returned to a standard service rate. The AC disconnect will be locked off and the on-site generation meter exchanged for a standard service meter. If the system is brought back online at a later date or moved to a new location, it must meet the current requirements and complete the interconnection process, including a new application. If a Legacy system is offline for longer than six months, or is moved to another site, the Legacy status is forfeited.
Ensuring your system is operating is your responsibility. Be sure to keep copies of all warranties. Track your monthly energy use and generation (if you have data monitoring) to look for abnormal changes in use. These may indicate an issue.
Idaho Power’s My Account online portal has hourly data and will record the excess energy each hour you push power to the grid.
Existing customers may choose to convert their existing two-meter design to a single-meter option; however, Legacy status would be forfeited. The customer will be responsible for costs to reconfigure the system and must complete the interconnection process, including a new application.
Idaho Power’s My Account tool allows customers to access a wide variety of information including usage data, excess energy delivered to the grid, and even access to past bills. Usage data is provided on an hourly, daily, monthly and yearly basis. Hourly usage data is available for download.
Some systems come with monitors that measure the energy produced by your renewable energy system. These monitors measure the total amount of energy being produced by the system before the energy flows into your home or business. If your system is producing more energy than the home needs at a given moment, the extra energy flows to Idaho Power. Our meters measure that excess energy only.
Excess Generation Credit Transfers
- Excess energy credits must be available at the designated meter.
- Service agreements must be held by the customer and be for the customer’s use.
- Service agreements must be on the same contiguous property and be served by the same primary feeder.
- Transfers can only occur between Residential and Small General Service accounts (Schedule 1, 6, 7 and 8) or between Large General, Large Power and Irrigation accounts (Schedule 9, 19 and 24).
- If multiple meters are eligible for aggregation, excess credits must first be applied to the designated meter, then to eligible meters on rate schedules in accordance with the criteria detailed above.
It is not necessary to apply for transfer if you wish to retain all credits at the existing meter. Credits that are not transferred will remain with the current service agreement.
It is not necessary to apply for transfer if you wish to retain all credits at the existing meter. Credits do not expire. Credits that are not transferred will remain with the current service agreement.
All systems
- Excess generation credits must be available.
- Service agreements must be held by the customer and be for the customer’s use.
Net Energy Metering (Legacy) systems only
- Service agreements must be on the same contiguous property and be served by the same primary feeder as the customer generation (i.e. on-site generation) service agreements.
- Transfers can only occur between Residential and Small General Service accounts (Schedule 1, 6, 7, and 8) or between Large General, Large Power, and Irrigation accounts (Schedule 9, 19, 24 and 84).
- If multiple meters are eligible for aggregation, excess net energy credits must first be applied to the designated meter, then to eligible meters outlined above.
Additional changes for Net Billing (Non-Legacy) customers
- kWh credits accrued before 2024:
- Remaining kWh credit balances can be used for a full year, provided the customer maintains electric service at the same service point.
- On December 31, 2024, any remaining kWh credits will be converted to a comparable financial credit using a blended average retail energy rate. This financial credit may be applied to monthly charges.
- Financial credits accrued since 2024:
- If a customer moves, they may request credits be applied to their new account.
- If a customer ends service and does not intend to establish service at another location in Idaho Power’s service area, any unused credits will be paid out following the time the final bill is prepared.
Schedule 68 (Non-export Option)
Some customers do not want their generation systems, like solar panels, to export power to the electrical grid and wish to interconnect their system so they consume all energy generated on-site. However, these systems are still grid-connected and, as such, need rules in place to ensure they do not negatively impact the grid. Schedule 68 outlines (1) technical solutions to prevent export; (2) an interconnection and application process so Idaho Power can verify compliance with the interconnection requirements and (3) mitigation efforts should the customer’s system export power beyond the allowable amount, referred to as the inadvertent export limits.
Under both the export and non-export options, residential (Schedule 01) and small general service (Schedule 07) generation systems are limited to a maximum AC size of 25 kilowatts (kW) (or kilovoltampere [kVA]). This limit will allow these customer groups to transition between non-export and export (by submitting an application) without making costly retrofits to their systems.
Large general service (Schedule 09), irrigation (Schedule 24) and industrial (Schedule 19) customers may install up to 100 kW (VA) AC for exporting systems. There is no limit to system size for non-exporting systems for these customer groups.
All customer generation applications will undergo a Feasibility Review to determine Idaho Power’s electrical grid’s capability to incorporate the proposed generation system and to determine if upgrades are necessary. In some cases, proposed systems may require an additional Feasibility Study to determine if upgrades or protection equipment is needed. Idaho Power will conduct Feasibility Studies for systems under 3 megawatts (MW) on a case-by-case basis. Systems over 3 MW will require additional study.
- Advanced Functionality: Use of an internal transfer relay, energy management system or other customer-owned facility hardware or software system(s) to ensure power is never exported across the interconnection point.
- Reverse Power Protection: Uses a reverse power relay to ensure power is never exported across the interconnection point.
- Minimum Power Protection: Uses an under-power protective function to ensure a minimum amount of power is consumed at all times, and therefore, power cannot be exported.
Customers whose systems export above the allowed inadvertent export limits (three hours of the distributed energy resource’s total nameplate capacity in any 30-day period) will be notified and expected to take corrective action.
For residential (Schedule 01) and small general service (Schedule 07) customers, the inadvertent export must be rectified within 30 days. After 30 days, the customer may elect to turn off the system or move to Schedule 6 or 8 (exporting service). For Schedules other than 1 or 7, the customer must immediately open the AC disconnect until the issue that caused the export is remedied.
For assistance with a PDF on this page or to request a PDF in an alternate format, please contact Customer Service at 208-388-2323 or 1-800-488-6151